Phase 4

Updates and information

For the final Phase of development and regeneration at Paintworks, Verve have joined forces with Rengen.

You will find information and updates about work on the site on this page.

Three Week 'Look Ahead' 8th June - 29th June 2020

Stage 2 Piling Commencement

  • Construction of the capping beam is to be progressed 8th June on top of the sheet piles alongside Central Road.
  • ‘STAGE 2’ Driven piling works have been delayed and are to be progressed w/c 15th June (for an anticipated duration of three weeks).
  • We are very grateful for your patience whilst we completed some of the most noisy and disruptive works on site during ‘lockdown’.

Traffic Management Plan

Working Hours

  • The working hours for the site will be 07:30-18:00 Monday to Friday and 08:00-13:00 Saturday. No working on Sunday.

Proposed Traffic Control Measures

  • A ‘travelling’ banksman will assist all Large goods vehicles entering the site during all piling works
  • The main contractor proposes that the majority of deliveries will be between 07:30am to 16:30 (this is within the planning timescales from 07:30-18:00) and deliveries outside of this timeslot will require prior approval
  • Large goods vehicles will be assisted down the Main Entrance/Exit road and through the site with the ‘travelling’ banksman
  • Stop / go signs and vehicle barriers will be used as necessary on site during piling works

Loading and Unloading of Plant & Materials / Delivery Frequency of Large Vehicles

  • When Large vehicles are due to site, the banksman will move to the top of the Main Entrance/Exit Road and will accompany the vehicle down the Main Entrance/Exit road to ensure any potential conflicts are avoided
  • It is proposed that a strict and co-ordinated delivery schedule is adhered to
  • The ‘travelling banksman’ will ensure that deliveries to site are effectively managed, and the general traffic movement through the site during all deliveries (both large and small) is not impeded

In case of emergency

The site manager Sam Gilbaro can be contacted on 07792 555 551 in case of emergency.

For more information about Phase 4 at Paintworks, please visit the Rengen website www.paintworksiv.com